This project included the repairs and resurfacing of a 5-mile stretch on the Ohio Turnpike main line from MP 69.30 to MP 74.15. DGL’s work consisted of milling and resurfacing the Eastbound and Westbound right and center lanes. Work also included bridge and guardrail repairs. DGL provided construction administration and construction inspection services for the entire construction duration. Due to MOT restrictions, the majority of the project construction occurred at night, so a key part of DGL’s responsibility included adequate full-time night inspection for the duration of the project. This project was completed in 2017. The construction cost for this project was $4,220,000.